Timeline for Milestones |
Feb. 2003 |
1st
prototype submission on MPW10.
(Kchip_v3) |
May. 2003 |
Kchip_V3 reception and packaging
on CPGA packages. |
Prepare TesterBoard
for CPGA package. |
June. 2003 |
Functionality
verification tests. |
Debugging. |
Oct. 2003 |
Prepare 2nd
prototype version for submission on MPW12. (Kchip_V3b) |
Nov. 2003 |
Kchip_V3b submitted. |
|
Year 2003
- Kchip_V3 submission on MPW10.
- Functionality verification and debugging.
- Update prototype design.
- Kchip_V3b submission.
Year 2004
- Package Kchip_V3b on CPGA package for preliminary
tests.
- Package Kchip_V3b on fpBGA.
- In system tests.
|